CHAPARRAL

Search for an article from Chaparral

 

More Change Ahead for GCC

by Andrew Young, Mathematics Division

Although some folks think we’ve had enough construction on campus, several more major construction projects are in the planning stage for GCC.  The next project is a substantial expansion of the Garfield Campus.  A second major building will be constructed, similar in overall design and physical size to the current main Garfield campus building, but with classrooms and offices on all three floors instead of having ground-level parking under the building.  The planned 33,000 square feet of new space will include about 13 new classrooms, which will allow the college to replace the old, substandard bungalows that currently house many classes.  It will also allow the college to consolidate some of the course offerings that are currently spread out in various spaces rented in non-college-owned buildings in the area surrounding the Garfield Campus.  This will still leave plenty of space to include faculty/staff office space, a vending machine area, and a large space to support community gatherings.

  Garfield Campus
 

Expansion of the Garfield Campus is scheduled to start construction in spring 2008.

     Another important component of the project is that it also will provide additional parking on college property.  The Garfield Campus has long suffered parking difficulties no less challenging than those of the main campus.  The 125 additional parking spaces that the new construction includes will help alleviate, but probably not completely solve, parking problems there.

     To allow space for both the new building and additional parking, the college needed to acquire three privately owned properties adjacent to the existing Garfield Campus.  Two of the three properties are already in escrow and the third is still under negotiation.  The current preliminary design also proposes permanently closing a portion of Garfield Avenue adjacent to the Garfield Campus, partially for use as parking, and the rest for a small “green belt.”

Design-Build could cut costs

     The Garfield expansion is one of only a handful of projects statewide that have been approved for a pilot program exploring the use of a new style of construction planning and execution known as Design-Build.  This method is expected to significantly reduce both the total cost and the duration of the project.  If the process goes as planned, the project will go to bid in early 2008, with construction beginning in spring 2008 and occupancy expected in time for fall 2010 classes.  Tight control on costs is particularly important for this project because the entire cost is to be paid out of Measure G funds.  Twenty million dollars have been allocated for use in this project, and if there is a cost-overrun, there is no obvious source of additional funds available.

     Virtually all of the rest of the remaining Measure G funds ($19 million) are allocated to cover the college’s portion (about 25%) of the total cost of constructing the new Laboratory/College Services building.  This building will be located on the main campus east of (behind) the cafeteria along the base of the hillside below the new parking structure.  It will stretch from the new elevator tower at the north end to (and including) the current location of the Los Robles building.  Only through careful planning for the space allocation within the building has the college managed to get the state to commit to funding about 75% of the total cost of construction (probably more than $60 million).  The administration and the college’s architect should be commended for their efforts in this area, without which this project would surely have been impossible for the college to finance.

And they paved the parking lot to put up a building

     The three-story Laboratory/College Services building will provide more than 80,000 square feet of space, including a large open computer lab, instructional labs for speech and writing, the Culinary Arts program, and almost all of Student Services.  Though the building was originally specifically intended to offer students “one-stop” access to all the services they need, there is still some question as to whether it will be possible to achieve this goal (despite a substantial increase in total allocated square footage over the current space being used by these same programs).

Culinary

Culinary Arts is scheduled to move to the new College Services building.

 

Design decisions must be finalized soon, because funding for this project has already been approved and scheduled.  Funds for preliminary drawings have been released, after which final drawings will have to be completed, and state approvals must be obtained.  Construction is expected to begin in 2009, leading to occupancy in fall 2012.  There is little room for delay.  Any significant design changes could force an additional cycle of project approvals, and potentially could lower the project’s funding priority.  Worse yet, any delay in the start of construction could increase construction costs by millions of dollars, much like what happened when the Allied Health/Aviation building had to be redesigned and re-approved.  That delay turned a $16 million project into a $24 million project. 

     A bit further down the pipeline is a major renovation of the Verdugo Gym and a possible modernization of the Aviation/Art building.  But these will have to be topics for a future update.

     I would like to thank Bill Taylor again for his time and patience explaining the details of all these projects.  Without his continuing assistance, these updates would be much more difficult to provide. &

back to top